Calculate the weight of a concrete slab, driveway, patio or wall being removed, the loose volume after breaking with swell, whether rebar or mesh is present, truck and dumpster loads, disposal or recycling cost, and the breaking time with a jackhammer or excavator.
How it works
Weight = area × thickness ÷ 12 × 150 lb/ft³ (× 1.05 mesh, × 1.08 rebar); loose yd³ = bank yd³ × (1 + swell); loads = max(weight ÷ capacity, volume ÷ capacity); time = area ÷ (rate × (4 ÷ thickness)^1.5 × reinforcement factor)
Concrete weighs about 150 pounds per cubic foot, so an ordinary 4-inch patio carries 50 pounds in every square foot and a modest driveway runs to ten tons or more — the reason removal jobs are quoted by weight and hauled in small, half-filled containers rather than the big boxes used for light debris. Breaking it up increases the volume by half but not the weight, and reinforcement adds both weight and, more importantly, time, since mesh must be snipped and rebar cut. Clean concrete is one of the most recycled materials in the world: crushed into road base it is accepted cheaply or free, while mixed loads pay full landfill rates, so keeping dirt and trash out of the pile is worth real money.
Worked example
A 600 ft² × 4″ patio with wire mesh is 200 ft³ of concrete — 15.8 tons — that breaks into about 11 yd³ of rubble. That is three half-filled 10 yd heavy-debris boxes (about 5 t each) at roughly $1,600 including a $25/t recycling fee, and around 15 labour-hours with an electric breaker before loading.
Frequently asked questions
Why can I only fill a 10 yd dumpster half way with concrete?
A full 10 yd box of rubble weighs 12–15 tons, beyond the legal road weight for the truck. Haulers mark a fill line and charge heavily if you exceed it.
How thick is my slab?
Patios and sidewalks 4″, driveways 4–6″, garage floors 4–6″ with thickened edges, commercial 6–8″. Drill a test hole or check an edge — thickness is the biggest variable in the weight.
Related calculators
Debris weights and volumes are typical industry averages (EPA, CDRA and hauler rules of thumb); actual density varies with moisture, compaction and mixing. Confirm weight limits and prohibited materials with your hauler and landfill, and check for asbestos and lead paint before demolition of pre-1980 buildings.