Kanban Card Quantity Calculator
Number of kanban cards or bins for a part from daily demand, replenishment lead time, container size and safety factor — loop inventory, coverage in hours and the effect of smaller containers.
How it works
Kanbans = (daily demand × lead time × (1 + safety factor)) ÷ container quantity, rounded up (minimum 2); loop inventory = cards × container quantity
A kanban loop caps inventory between two process steps: each card (or bin) authorises one container of parts, and when a container is emptied its card travels back as the signal to replenish. The number of cards must cover the demand that occurs while a replenishment is in flight, plus a safety allowance for demand spikes and late deliveries; anything more is waste, anything less stops the line. Because the formula divides by container size, halving the bin roughly halves the inventory for the same protection — at the cost of more trips — which is why lean systems push for small, frequent containers and shorter replenishment loops rather than larger buffers. Recalculate whenever demand shifts by more than about 10%, and remove cards deliberately to expose problems.
Worked example
400 parts a day, a 1.5-day replenishment loop, bins of 50 and 20% safety: 400 × 1.5 × 1.2 ÷ 50 = 14.4 → 15 cards holding 750 parts (1.9 days, $6,000). Bins of 25 would need 29 cards but only 725 parts.
Frequently asked questions
What safety factor should I use?
10–20% for reliable internal loops, 30–50% for external suppliers or variable demand; reduce it as the loop proves itself.
Lead time in days or hours?
Either, as long as demand uses the same unit; include the full loop — signal transport, waiting, production or picking, and delivery back to the point of use.
Related calculators
Operations planning estimate based on the figures entered; validate against measured shop-floor data before changing staffing, equipment or customer commitments.