Earned Value Calculator (EVM: CPI, SPI, EAC)

Earned value management in one step: enter budget at completion, planned value, earned value and actual cost to get CV, SV, CPI, SPI, EAC, ETC, VAC and TCPI for your project.

Budget at completion (BAC)
Planned value (PV)
Earned value (EV)
Actual cost (AC)
Loading calculator…

How it works

CV = EV − AC · SV = EV − PV · CPI = EV ÷ AC · SPI = EV ÷ PV · EAC = BAC ÷ CPI · ETC = EAC − AC · VAC = BAC − EAC · TCPI = (BAC − EV) ÷ (BAC − AC)

Earned value management (EVM) compares three numbers at a status date: planned value (what should have been done), earned value (the budgeted cost of what was actually done) and actual cost (what was spent). An index below 1.0 is unfavorable: CPI < 1 means each unit of money buys less work than planned, SPI < 1 means work is behind plan. The PMI PMBOK Guide and the US GAO Cost Estimating and Assessment Guide use the same formulas; BAC ÷ CPI is the standard EAC when current cost efficiency is expected to continue.

Worked example

A project with BAC $100,000 is at its status date with PV $50,000, EV $40,000 and AC $45,000. CV = 40,000 − 45,000 = −$5,000 and SV = 40,000 − 50,000 = −$10,000. CPI = 40,000 ÷ 45,000 = 0.889 and SPI = 40,000 ÷ 50,000 = 0.800, so the project is over budget and behind schedule. EAC = 100,000 ÷ 0.889 = $112,500.00, ETC = $67,500.00, VAC = −$12,500.00, and the remaining work must run at a TCPI of 60,000 ÷ 55,000 = 1.091 to finish on budget.

Sources: US GAO — Cost Estimating and Assessment Guide (GAO-20-195G), earned value chapter · Earned value management — formulas

Frequently asked questions

What do CPI and SPI tell you?

CPI (EV ÷ AC) is cost efficiency: 0.889 means you get 89 cents of planned work for every dollar spent. SPI (EV ÷ PV) is schedule efficiency: 0.80 means you have completed 80% of the work planned by now. Above 1.0 is good, below 1.0 is a warning.

Which EAC formula should I use?

BAC ÷ CPI assumes the cost overrun so far will continue — the most common default. AC + (BAC − EV) assumes the rest of the work will go exactly to budget (only for one-off problems). AC + (BAC − EV) ÷ (CPI × SPI) is the pessimistic case when a late project must also be accelerated.

How do I get earned value?

Multiply the budget at completion by the percentage of work actually completed, or add up the budgets of finished work packages. A $100,000 project that is 40% done has earned $40,000 of value, no matter what has been spent.

What is a good TCPI?

TCPI is the cost efficiency the remaining work must achieve to finish on budget. Close to 1.0 is realistic; above about 1.10 is rarely achieved in practice, which is a sign the budget should be re-baselined.

Why is SPI misleading near the end of a project?

At completion EV equals PV, so SPI returns to 1.0 even if the project finished months late. For late-stage schedule analysis, use earned schedule or the critical path instead.

Related calculators

Earned value forecasts are only as good as the percent-complete estimates behind them; review them with your project controls team.